My Renovation Project

Master Suite & Living Room Redesign · Started April 14, 2026

Last updated July 2, 2026 · 9:42 AM

Project Progress

Master Suite & Living Room Redesign

Construction Phase
Disc.
Design
Proc.
Const.
Finish
Over
Overall Completion50%

3 of 6 phases complete · Est. 3 phases remaining

Contractor

Marcus Aldridge Design Co.

Project Manager

Marcus Aldridge

Scope

Master Suite + Living Room

Est. Completion

September 12, 2026

Total Budget

$48,500

Invoiced to Date

$31,200

Project completion

3

Deliverables Due

2 this week

$4,800

Outstanding Invoices

2 invoices pending

2

Unread Messages

From your contractor

11

Shared Documents

3 new this month

Project Deliverables

3 of 8 milestones complete

Final Design Presentation

May 10, 2026Completed

Full room-by-room design boards with material and finish selections

Design Phase

Material Procurement Confirmation

Jun 1, 2026Completed

Signed purchase orders for all specified materials and fixtures

Procurement Phase

Structural Demolition Sign-Off

Jun 20, 2026Completed

Client approval of completed wall removal and rough framing

Construction Phase

Electrical & Plumbing Rough-In Inspection

Jul 8, 2026In Progress

City inspection pass for all rough-in work before drywall

Construction Phase

Master Suite Drywall & Texture Completion

Jul 22, 2026Upcoming

All drywall hung, taped, mudded, and textured in master bedroom

Construction Phase

Cabinet & Millwork Installation

Aug 5, 2026Upcoming

Custom cabinetry installation in master suite walk-in and living room built-ins

Finishing Phase

Paint & Finish Walkthrough

Aug 19, 2026Upcoming

Client walkthrough of completed paint, trim, and finish work for approval

Finishing Phase

Punch List & Final Walkthrough

Sep 5, 2026Upcoming

Final deficiency list review and sign-off for project handover

Handover Phase

Invoices

Payment history for your project

Paid

$31,200

Outstanding

$8,000

InvoiceAmountStatusAction
INV-2026-041$8,500PaidPaid Apr 20, 2026
INV-2026-058$12,400PaidPaid May 15, 2026
INV-2026-072$10,300PaidPaid Jun 10, 2026
INV-2026-089$4,800Pending
INV-2026-094$3,200Overdue

Messages2

Direct line to your contractor

MA
Hi Sarah! The electrical rough-in inspection is scheduled for July 8th at 10 AM. The inspector will need access to the main panel — please make sure someone is home.
Jul 1, 9:14 AM
SH
Perfect, I'll be home that day. Should I do anything to prep the space before the inspector arrives?
Jul 1, 11:32 AM
MA
Just keep the area around the panel clear — about 3 feet on all sides. We'll handle the rest. Also, I've uploaded the updated material schedule to your documents section.
Jul 1, 2:05 PM
MA
Quick reminder: Invoice INV-2026-094 for the custom tile balance is due July 5th. Let me know if you have any questions about the line items.
Jul 2, 8:30 AM

Documents

6 files shared on this project

Upload a file or drag & drop

Design_Concept_Boards_v3.pdf

8.4 MB · May 8 · Design

Material_Schedule_Rev2.xlsx

1.2 MB · Jul 1 · Procurement

Electrical_Permit_2026.pdf

340 KB · Jun 15 · Permits

Signed_Contract_Harrington.pdf

1.8 MB · Apr 12 · Contracts

Inspiration_Board_Client.pdf

5.1 MB · Apr 14 · Design

Plumbing_Rough_In_Photos.zip

22.3 MB · Jun 28 · Progress